Listing of Advertised Projects LAST UPDATED: FEBRUARY 06, 2012 ATTENTION PROSPECTIVE BIDDERS: The Bid Documents may be obtained by contacting the District's Public Counter at (562) 908-4288, extension 1205. The District does not warrant the accuracy or completeness of Bid Documents obtained from any source other than the District's Public Counter, and any use of such documents by prospective bidders or others for any purpose is solely at the bidders' risk. For technical questions concerning the plans and specifications and/or further information regarding the status of a particular project, contact the Project Manager at the extension number provided at (562) 908-4288. PROJECT NAME / DOLLAR RANGE | ADVERTISE | WALK- THROUGH | BID | AWARD | WORKING DAYS | Puente Hills Landfill Gas Collection System-2012 (John Chung, Ext.: 2183 - approx. $1,500,000 - $2,600,000) Plan Holder List
Apparent Low Bidder - Humphery Constructors ($1,858,400.00)
Bid Item Sheet
Bid Results | 12/15/11 | Mandatory 01/10/12 01:00 p.m. | 02/02/12 | 02/22/12 | 350 | Puente Hills Landfill Drainage Improvements-2012 (John Chung, Ext.: 2183 - approx. $525,000 - $875,000) Plan Holder List
Bid Item Sheet | 01/12/12 | Mandatory 02/07/12 01:00 p.m. | 03/06/12 | 03/28/12 | 120 | Oak Street-Center Avenue Relief Trunk Sewer Rehabilitation-2012 (Melissa Fischer, Ext.: 6807 - approx. $63,000 - $77,000) Plan Holder List
Bid Item Sheet | 01/19/12 | N/A | 02/23/12 | 03/21/12 | 40 | Long Beach Water Reclamation Plant Interceptor and Bloomfield Pumping Plants Installation of Pumps (Melissa Fischer, Ext.: 6807 - approx. $112,500 - $187,500) Plan Holder List
Bid Item Sheet | 01/26/12 | Mandatory 02/14/12 10:00 a.m. | 03/01/12 | 03/28/12 | 125 | Joint Outfall "F" Unit 3C Rehabilitation-2011 (Melissa Fischer, Ext.: 6807 - approx. $135,000 - $225,000) Plan Holder List
Apparent Low Bidder - Repipe California ($255,970.00)
Bid Item Sheet
Bid Results | 12/22/12 | N/A | 01/17/12 | 02/08/12 | 40 |
PUENTE HILLS LANDFILL GAS COLLECTION SYSTEM-2012 (Mandatory walk-through location: Puente Hills Materials Recovery Facility Parking Lot
2800 S. Workman Mill Road
Whittier, California 90601) — The project consists of constructing approximately 18,000 linear feet of polymer coated corrugated steel pipe gas collection trenches, approximately 2,100 linear feet of gas collection header, approximately 3,000 linear feet of 3-inch condensate piping, and all other appurtenant work. All trenching will be conducted beneath the odor control tent. PUENTE HILLS LANDFILL DRAINAGE IMPROVEMENTS-2012 (Mandatory walk-through location: Puente Hills Landfill
13130 Crossroads Parkway South
City of Industry, CA 91746) — The proposed project consists of demolition and reconstruction of portions of an existing detention basin including installation of an HDPE liner; construction of approximately 1,500 feet of concrete trapezoidal channel and approximately 600 feet of HDPE storm drains; modifications to an existing liquids management system including installation of an wireless auto dialer system to communicate high liquid level alarm; and all other appurtenant work. OAK STREET-CENTER AVENUE RELIEF TRUNK SEWER REHABILITATION-2012 — The proposed project rehabilitates approximately 67 feet of 21-inch diameter reinforced concrete pipe sewer with a cured-in-place pipe liner or spiral wound PVC liner, and all appurtenant work.. LONG BEACH WATER RECLAMATION PLANT INTERCEPTOR AND BLOOMFIELD PUMPING PLANTS INSTALLATION OF PUMPS (Mandatory walk-through location: 6330 Atherton Street
Long Beach, CA 90815) — The proposed project will remove two existing pumps and install two District-furnished pumps, and include the construction of reinforced concrete pump bases, piping modifications, electrical connections and all appurtenant work to make the pumps operational and maintain facility functionality, and all appurtenant work.. JOINT OUTFALL "F" UNIT 3C REHABILITATION-2011 — The proposed project rehabilitates approximately 67 feet of 54-inch diameter reinforced concrete pipe with a cured-in-place or spiral wound pipe liner, and all appurtenant work. The project is located within the City of Norwalk at the intersection of Alondra Avenue and Gridley Road. |