Listing of Advertised Projects

LAST UPDATED: APRIL 26, 2018

ATTENTION PROSPECTIVE BIDDERS: The Bid Documents may be obtained by contacting the Sanitation District's Public Counter at (562) 908-4288, extension 1205. The Sanitation District does not warrant the accuracy or completeness of Bid Documents obtained from any source other than the Sanitation District's Public Counter, and any use of such documents by prospective bidders or others for any purpose is solely at the bidders' risk.

For technical questions concerning the plans and specifications and/or further information regarding the status of a particular project, contact the Project Manager at the extension number provided at (562) 908-4288.

PROJECT NAME /
DOLLAR RANGE

ADVERTISE

WALK-
 THROUGH 

BID

AWARD

WORKING
DAYS

Calabasas Landfill Gas Collection System-2018 (Ethan Laden, Ext.: — approx. $550,000 — $950,000)

Plan Holder List

Bid Item Sheet

03/01/18

Mandatory
03/15/18
10:00 AM

05/29/18

06/27/18

60

Joint Water Pollution Control Plant Demolition of Digestion Tanks KLM (Derek Zondervan, Ext.: 2107 — approx. $4,500,000 — $5,500,000)

Plan Holder List

Bid Item Sheet

03/01/18

Mandatory
03/20/18
10:00 AM

04/26/18

05/23/18

160

Old River School Road Relief Trunk Sewer Rehabilitation Phase 2 (Jenny Hsu, Ext.: 1618 — approx. $1,300,000 — $2,300,000)

Plan Holder List

Apparent Low Bidder - Insituform Technologies, LLC ($2,297,748.00)

Bid Item Sheet

Bid Results

03/15/18

Mandatory
03/29/18
10:00 AM

04/17/18

05/09/18

160

Belvedere Trunk Sewer Rehabilitation, Phase 1 (Jenny Hsu, Ext.: 1618 — approx. $1,200,000 — $2,300,000)

Plan Holder List

Bid Item Sheet

04/05/18

Mandatory
04/18/18
10:00 AM

05/15/18

06/13/18

220

Lancaster Water Reclamation Plant Eastern Agricultural Site Groundwater Extraction Wells Installation (Stanley Pegadiotes, Ext.: 2705 — approx. $1,500,000 — $2,100,000)

Plan Holder List

Bid Item Sheet

04/12/18

N/A

05/22/18

06/21/18

120

Joint Water Pollution Control Plant Secondary Treatment Concrete Repair-Phase II (Tamara Nikonova, Ext.: 2152 — approx. $15,000,000 — $19,000,000)

Plan Holder List

Bid Item Sheet

04/17/18

Mandatory
05/03/18
10:00 AM

05/22/18

06/27/18

1140

Joint Administration Office Restroom Reconstruction (Tamara Nikonova, Ext.: 2152 — approx. $900,000 — $1,900,000)

Plan Holder List

Bid Item Sheet

04/26/18

Mandatory
05/15/18
10:00 AM

06/05/18

07/11/18

260


CALABASAS LANDFILL GAS COLLECTION SYSTEM-2018(Mandatory walk-through location: 5300 Lost Hills Road, Agoura, California 91301) — The project consists of construction of approximately 7,618 linear feet of gas collection trenches, 800 linear feet of gas collection header, 200 linear feet of condensate piping, and six (6) gas trench-to-header connections.
JOINT WATER POLLUTION CONTROL PLANT DEMOLITION OF DIGESTION TANKS KLM(Mandatory walk-through location: 24501 South Figueroa Street, Carson, California 90745) — The project will involve demolition of the existing Digestion Tanks KLM and ancillary facilities, including removal and disposal of existing residuals within the tanks; demolition of existing mechanical piping and equipment; demolition of existing above-and below-grade reinforced concrete tank structure; removal and relocation of civil yard piping and electrical equipment; and backfill to match existing grade, and all appurtenant work.
OLD RIVER SCHOOL ROAD RELIEF TRUNK SEWER REHABILITATION PHASE 2(Mandatory walk-through location: 7346 Dinwiddie Street, Downey, California 90241 (just west of intersection with Old River School Road)) — The work consists of rehabilitation of approximately 5,364 feet of existing 18-, 24-, 27- and 33-inch diameter vitrified clay pipe (VCP) and reinforced concrete pipe (RCP) on the Old River School Road Relief Trunk Sewer and Old River School Road Trunk Sewer with cured-in-place pipe (CIPP) liners, and all appurtenant work. Two (2) segments are located along the existing sewer alignment beginning approximately 270 feet east of Karmont Avenue, then easterly and northerly through private property and along Old River School Road, and ending in Old River School Road approximately 100 feet north of Firestone Boulevard. One (1) segment is located along the existing sewer alignment beginning in private property near the intersection of Old River School Road and Imperial Highway and ending in Old River School Road at the intersection of Leeds Street.
BELVEDERE TRUNK SEWER REHABILITATION, PHASE 1(Mandatory walk-through location: Bristwo Park, 1466 S. McDonnell Avenue, Commerce 90040) — The work consists of rehabilitation of approximately 10,260 feet of existing 15-inch, 21-inch and 24-inch diameter cracked vitrified clay pipe on the Belvedere Trunk Sewer with cured-in-place pipe (CIPP) liners. The project will also rehabilitate thirty-nine (39) existing manholes with calcium aluminate cement, and all appurtenant work. The project comprises twelve (12) segments located within the cities of Commerce, Monterey Park, and unincorporated Los Angeles County. Three (3) segments within the City of Commerce are located along the existing sewer alignment beginning at the intersection of Astor Avenue and Barney Street, then northwesterly and westerly through private property, and ending at the intersection of Noakes Street and Downey Road. Seven (7) segments within unincorporated Los Angeles County are located along the existing sewer alignment beginning approximately 300 feet north of the intersection of Downey Road and Triggs Street, then northerly along public right of way, and ending approximately 300 feet north of the intersection of 1st Street and Sunol Drive. Two (2) segments within the City of Monterey Park are located along the existing sewer alignment beginning approximately 230 feet northeast of the intersection of Blanchard Street and McBride Avenue, then northeasterly through public right of way, and ending approximately 500 feet east of McBride Avenue.
LANCASTER WATER RECLAMATION PLANT EASTERN AGRICULTURAL SITE GROUNDWATER EXTRACTION WELLS INSTALLATION — The project consists of the construction of three (3) 16-inch diameter, 1,400-foot deep groundwater extraction wells, each including a vertical turbine pump, discharge head, right angle pump drive, diesel exhaust fluid tank, reinforced concrete pad, fencing, and all appurtenant work, within District's property located between 70th Street East and 90th Street East and between Avenue E and Avenue G in unincorporated Los Angeles County, northeast of the City of Lancaster, California (NOTE: PROJECT DURATION IS 120 CALANDAR DAYS NOT WORKING DAYS).
JOINT WATER POLLUTION CONTROL PLANT SECONDARY TREATMENT CONCRETE REPAIR-PHASE II(Mandatory walk-through location: Joint Water Pollution Control Plant, 24501 S. Figueroa Street, Carson, CA 90745) — The work consists of furnishing all materials, equipment and labor, demolition of existing deteriorated concrete portions of secondary clarifiers and replacing with new concrete, demolition of existing foam spray piping and installation of new foam spray piping and demolition of existing aluminum handrails and installation of new handrails, and all appurtenant work.
JOINT ADMINISTRATION OFFICE RESTROOM RECONSTRUCTION(Mandatory walk-through location: County Sanitation Districts (Joint Administration Office), 1955 Workman Mill Road, Whittier, CA 90601) — The work consists of furnishing all materials, equipment, and labor, including all appurtenant thereto, for renovation of four(4) restrooms including complete replacement of plumbing and lighting fixtures, piping, mixing boxes, ductwork, walls, ceilings, and floors, and installation of automatic doors, and all appurtenant work.